ASSESSEMENT
1.
Creation secondary cost element
: i.e (that is) assessment cost element :
Path: Accounting
–Controlling –Cost element accounting-Mater data-Cost element –Individual
processing –Create secondary (KA06)
Give the
controlling area :BIL
Enter
Cost element :1000000
Valid from :01.04.2008 to 31.12.9999
Enter
Name and
description :Assessment cost
element.
Cost element
category :42
(Assessment )
Save
2.
Define Co.No.range interval for
the business truncation- RKIU-Actual overhead assessment
Use
the Truncation code :KANK
Give the
controlling area :BIL
Select maintain
groups button
Double click on
RKIU
Select Co.No.range
interval for BIL check box
From the menu
select Edit –Assignment element group.
Ignore the message
press enter
Creation
of assessment cycle:
Accounting –Controlling –Cost center accounting-Period
and closing –Current settings–Define assessment (Tr.code S_ALR_87005742)
Give the cycle :BIL1
Start date :01.04.2008
Enter
Text :
Assessment cycle
Select iterative check box.
Select save button or Ctrl+S
Press enter to save in your request
Select iterative check box
Dept C Dept A 60% 300000 54000
Salaries 500000 Dept B 30% 150000 27000
Less :Allocation 500000 Dept
Z 10% 50000 9000
--------
0
Add: Allocation 90000
Less :Allocation 90000
-------
0
Add: Allocation 1800
Dept Z
Wages 400000 Dept X 50% 225000 4500
Add: Allocation 50000 Dept Y 30% 135000 2700
--------
450000 Dept C 20% 90000 1800
Less : Allocation 450000
-------
0
====
We have to run
number of items to make both cost center values zero. If we select interactive
check box, system will run number of items automatically till both cost center
values become zero.
Select attaché
segment button.
Segment name : Segment 1
Description : Salaries
allocation
Assessment cost
element :select 1000000
Sender rule :select posted amounts
Share in % :100
Select actual
value origin radio button
Receiver rule :Select variable
portions
Variable portion
type :Select actual
statistical key figures
Select sender /
receivers tab
Sender cost center
:Dept C
Under Cost element
:400100
(Salaries a/c)
Under Receiver
cost center group :BILHYDPROD
Select receiver
tracing factor tab
Statistical key
figure :EMP
Select receiver
weight factors tab
Select save button
or Ctrl+S
Press enter to
save in your request
Select attaché
segment button
Segment name
segment2
Description :Rent allocation
Assessment cost
element :1000000
Sender rules :Posted amount
Sharing in % :100%
Select actual
value origin radio button
Select receive
rule :Fixed percentages
Select senders/
receivers tab
sender cost center
:Dept C
Cost element :400300 (Rent )
Receiver cost
center group : BILHYDPROD
Select receiver
tracing factor tab
Dept A 70
Dept B 30
Save
Press enter to
save in your request
Go
and see the cost center Report (Tr code
is KSB1)
Give the cost center :Dept C
Posting date :01.10.2008 to 31.10.2008
Execute
Select cost element column
Select sub totals button
Dept C A
B
Salaries 1500000 No.of employees
500
250
100000 50000
Rent 25000 Percentage basis
70
30
17500 7500
Execution
of assessment cycle:
Path :Accounting –Controlling –Cost center accounting
–Period end closing-Single functions-Allocations –Assessment (KSU5)
Give the period :7 (October)
Fiscal year :2008
Deselect text run
check box
Select details
list check box
Cycle select :BIL1
Execute
Select receiver
button
No comments: